ASSOCIATED ADMINISTRATIVE REGULATION:
400.31
ADOPTED:
CTESS Process Timeline
Orientation
- Completed at least fifteen (15) school days prior to the first formal IPOP
Self-Assessment: Professional Learning Goal
- September 30 – Professional Learning Goal submitted to the evaluator
Student Growth Goal
- October 30 – Student Growth Goal submitted to the evaluator
Beginning-of-Year Conference (BYC)
- October 6 – Professional Learning Goal feedback provided
- November 5 – Student Growth Goal feedback provided
Instructional Priorities Observation Protocol (IPOP)
- May begin fifteen (15) school days after the orientation
Feedback for Provisional Educators (Year 1)
- November 30 – Two formal IPOPs completed for provisional educators (Year 1)
Analysis/Response to Stakeholder Feedback
- December 15 – Response Statement regarding student and parent feedback
Mid-Year Conference: Instructional Quality Rating (IQR)
- January 30 – IQR completed for provisional educators (Years 2 and 3)
- March 30 – IQR completed for provisional educators (Year 1), probationary educators, and career educators in Phase Three
Student Growth
- April 30 – Response Statement regarding Student Growth Data
End-of-Year Conference: Summative Overall Rating (SOR)
- May 30 – Summative Overall Rating completed for all provisional educators, probationary educators, and career educators in Phase Three
This online presentation is an electronic representation of the Canyons School District’s currently adopted policy manual. It does not reflect updating activities in progress. The official, authoritative manual is available for inspection in the office of the Superintendent located at 9361 South 300 East Sandy, UT 84070.